Project Progress no. 1

There is not much progress achieved so far since i was very busy with my work. So i need to rely on my father in law to arrange all the front end activities i.e. barn layout, barn foundation etc.

Our progress meeting always take place during the dinner.

Last night discussion was:
1. Barn layout 80% completed. 30' x 15' barn cost us around 5k.
2. Foundation - require 4 - 5 lorries of soil. cost us around 1k.
3. Fence - cost us around rm600.


We plan to complete all the barn work by end of April, Insya-Allah.

But the problem now is i'm difficult to find the good supplier for the goat. Where can i get the cheapest goat, huh??

We plan to have around 10 - 20 goats for the starting.

My father in law designs the barn himself-he`s very good at it.He was the one who design the present house-vey unique.

2 comments:

Farra Da Smiley said...

khusyuk sungguh tok hussin buat design yer..mmg ala2 arkitek gitu :)

ada keje kosong tak kat saujana goats farm ni?

Wady said...

memang khusyu` gaya arkitek.hj hussin ni kalau nak buat apa2 mesti perancangan tip-top.kerja kosong takde lagi la..